Storage
a) When you lift
profile, you may have to spend more effort and pay attention to disassembly.
b) When stored on the site,be sure to put on a flat ground.
c) When the stacking profiles, should be placed from both ends of the joist, adjacent two joist center distance of not more than 60 cm,the joist should be arranged vertically with the profile.
d) Profile outdoor stacking to the whole bundle of packaging.smooth stacking, to prevent the sun burst sun deformation.
Installation
a) Profile for railings, must be inserted with
steel, and the floor to be absolutely strong, railings between the requirements
of each liner 450mm, to prevent deformation fall.
b) Profile for the pavilion or pergola, to consider
the coefficient of thermal expansion, and the tube, and the vertical to be
connected firmly.
c) Plastic has a certain plastic properties, so
when the length is greater than 3 meters, the material has a certain bend, easy
to correct when installed to normal, if the plastic section is a profile, the
bending deformation is relatively increased installation is able to basically
correct in place.
d) When the profile is installed upright, and the
length is greater than 2 meters, each end with four pairs of screws to fix. And
the vertical screw spacing of 40cm or more, so that each end of the four screwson average force
e)Under normal circumstances, profiles when the
joists required 30 cm span ( depending on the size of profile).
e)The self tapping screw is the first choice for
the installation of square Box, Rectangular Box & Profile.
f)During the installation, you must drill in
advance. The diameter of the pre-drilled hole should be less than 3/4 of the diameter of the straight or screw.
g)When the profile width is bigger than 10mm,each
end should be two screws. In special use conditions or extraordinary load
conditions – such as hot baths- installation may require shorter spacing.
h)The gap to take into account the drainage,
cleaning and a slight thermal expansion, contraction and other reasons, the
profile installation, edge to side, between the first and the first must leave the
appropriate gap. Edge to edge profile to the edge between the requirements
ofless than 4 mm. When installed in the
cold climate, gap requirements less than 5mm. Head –to-head the size f the gap
between the head and the head of the profile depends on the length of the
profile.
Cleaning
a)Contamination caused by molds, molds, berries and berries
and leaves use detergents containing detergents and sodium hyprochlorite
b)Rust and dirt the use of phosphoric acid
cleaning agent. In the home shopping malls and hardware stores can buy.
c)Caused by the touch of oil and grease pollution once
found to be contaminated, with a degreasing agent cleaning agent scrub
clean.Profile tips sandpaper can be used to polish grease pollution, polished
place just like the installation of profiles, will be affected by the climate
lead to slight change in color.
d)a)The regular use of tools to remove the gap at
the profile of debris, to ensure smooth drainage”.